June 25, 2026

Project Update 6/25/2026

This week the contractor completed demolition of the houses on the north side of 143rd Street at Naperville Road, placed[...]

READ MORE
June 18, 2026

Project Update 6/18/26

This week the contractor poured curb between Naperville Road and IL 126, installed traffic signal and lighting foundations and conduits,[...]

READ MORE
June 11, 2026

Project Update 6/11/26

This week the contractor poured curb along 143rd Street between IL 126 and Naperville Road, removed bridge overhang forms, installed[...]

READ MORE
June 4, 2026

Project Update 6/4/26

This week the contractor completed mainline paving of 143rd Street between IL 126 and Naperville Road, poured turn lanes, adjusted[...]

READ MORE