Open House Public Meeting Help shape improvements at the intersection of 143rd Street and Wallin Drive at US Route 30.[...]
Blog - Archive: April, 2026
Project Update 4/30/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/23/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/17/26
This week the contractor poured pavement and curb on Naperville Road, installed storm sewer along southbound IL 59, removed temporary[...]
Project Update 4/9/26
This week the contractor completed the remaining storm sewer work at IL 126 and Naperville Road, installed rebar and poured[...]
Project Update 4/2/26
This week, the contractor constructed the concrete slab on the west side of the bridge approach, prepared the forms and[...]
Showing 6 of 6 results
