This week, the contractor continued the sight screen fence installation, landscaping, general site clean-up, and the utility contractor continued relocation[...]
Blog - Archive: August, 2026
Project Schedule Update
Project Update 8/20/26
This week the contractor continued installation of the sight screen fence from Naperville Road toward the river, resumed utility relocations[...]
Project Update 8/13/26
This week, the contractor was limited by weather but was able to complete bridge painting, prep the abutments, piers, and[...]
Project Update 8/6/26
This week the contractor continued bridge painting, topsoil placement, installation of sight screen fence, lighting and traffic signal foundations, handholds,[...]
Showing 5 of 5 results