Project Update 6/18/26

June 18, 2026

This week the contractor poured curb between Naperville Road and IL 126, installed traffic signal and lighting foundations and conduits, completed the parapet wall on the bridge, graded the base between the curb and retaining wall along Fletcher Lake, formed the center median surface on the bridge, and installed driveways along Naperville Road and IL 126.

Next week the contractor will pour the center median on the bridge, continue traffic signal and lighting work, pour median surfaces between Naperville Road and IL 126, complete sidewalk ramps at Naperville Road and IL 126, place the asphalt shoulder between the curb and retaining wall along Fletcher Lake, and install fence panels along Fletcher Lake.

To view near real time views of construction progress, please check out the Webcam Feed, as well as the latest drone video update, on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.