This week the contractor continued installing parapet rebar on the bridge, removing temporary causeways, grading and placing topsoil under the[...]
Blog - Archive: March, 2026
Project Update 3/19/26
This week the contractor began removing temporary gravel construction road, continued parapet reinforcement, installed sight screen fence sleeves, and began[...]
Project Update 3/12/2026
Project Update 3/5/26
This week the contractor completed installation of fence posts along Fletcher Lake retaining wall, continued installation of bridge parapet reinforcement,[...]
Showing 4 of 4 results