May 28, 2026

Project Update 5/28/26

This week the contractor continued placing concrete between Naperville Road and IL 126 and installing trees, bridge parapet railing, bridge[...]

READ MORE
May 21, 2026

Project Update 5/21/26

This week, the contractor continued installing bridge median reinforcement and parapet railing, prepping for mainline pavement, placing asphalt on IL[...]

READ MORE
May 14, 2026

Project Update 5/14/26

This week the contractor continued installing the bridge bicycle railing, laid out locations for trees, brought in equipment for concrete[...]

READ MORE
May 7, 2026

Project Update 5/7/26

This week the contractor continued installing the bridge bike railing, poured the concrete bridge walls, finished the gateway monument signs,[...]

READ MORE