Project Update 1/22/26
This week, the contractor continued work on the Fletcher Lake retaining wall fence posts and foundations. All other planned activities[...]
Project Update 1/15/26
This week, the contractor continued removing bridge deck forms, formed and poured the bridge abutment blockout area, installed Fletcher Lake[...]
November 2025 – Drone Video Update
To view the progress of the East Extension of the 143rd project, please check out the November 2025 Construction Update[...]