Project Update 8/20/26
This week the contractor continued installation of the sight screen fence from Naperville Road toward the river, resumed utility relocations[...]
Project Update 8/13/26
This week, the contractor was limited by weather but was able to complete bridge painting, prep the abutments, piers, and[...]
Project Update 8/6/26
This week the contractor continued bridge painting, topsoil placement, installation of sight screen fence, lighting and traffic signal foundations, handholds,[...]
Project Update 7/30/26
This week the contractor continued bridge painting, traffic signal and lighting foundation and conduit installation, sight screen fence installation, landscaping,[...]
Project Update 7/23/26
This week the contractor continued bridge painting, installation of traffic signal and lighting foundations and conduits at the Naperville Road[...]
Project Update 7/16/26
This week the contractor continued painting the bridge over the DuPage River, installing traffic signal and lighting foundations and conduits,[...]
Project Update 7/9/26
This week, the contractor continued installing the sight screen fence along Fletcher Lake, as well as curb and gutter, median[...]
Project Update 6/25/2026
This week the contractor completed demolition of the houses on the north side of 143rd Street at Naperville Road, placed[...]
Project Update 6/18/26
This week the contractor poured curb between Naperville Road and IL 126, installed traffic signal and lighting foundations and conduits,[...]