• Home
  • Corridor Overview
    • 143rd Street & Wallin Drive at US Route 30 Intersection Improvements
    • East Extension
    • West Extension
  • Map
  • Schedule
  • Gallery
  • FAQs
  • Documents
  • Contact
  • Home
  • Blog
  • All Updates, East Extension
  • Project Update 8/20/26

Project Update 8/20/26

August 20, 2026

This week the contractor continued installation of the sight screen fence from Naperville Road toward the river, resumed utility relocations at IL 59 and landscaping along IL 126, 143rd Street, and Naperville Road, and performed general site clean-up.

Next week the contractor will continue with the sight screen fence installation, landscaping, and utility relocations.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

  • East Extension
  • Home
  • Village of Plainfield
  • Documents

All rights Reserved