• Home
  • Corridor Overview
    • 143rd Street & Wallin Drive at US Route 30 Intersection Improvements
    • East Extension
    • West Extension
  • Map
  • Schedule
  • Gallery
  • FAQs
  • Documents
  • Contact
  • Home
  • Blog
  • All Updates, East Extension
  • Project Update 5/14/26

Project Update 5/14/26

May 14, 2026

This week the contractor continued installing the bridge bicycle railing, laid out locations for trees, brought in equipment for concrete paving, began installing reinforcement in the bridge median, and continued final grading of the roadway base between Naperville Road and IL 126.

Next week the contractor will finish installing the bicycle railing and begin installing the pedestrian railing on the bridge, continue installing reinforcement in the bridge median, complete grading of the roadway base and start paving between Naperville Road and IL 126, and begin tree planting and landscaping between the DuPage River and IL 126.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

  • East Extension
  • Home
  • Village of Plainfield
  • Documents

All rights Reserved