This week the contractor continued installing the bridge bicycle railing, laid out locations for trees, brought in equipment for concrete paving, began installing reinforcement in the bridge median, and continued final grading of the roadway base between Naperville Road and IL 126.
Next week the contractor will finish installing the bicycle railing and begin installing the pedestrian railing on the bridge, continue installing reinforcement in the bridge median, complete grading of the roadway base and start paving between Naperville Road and IL 126, and begin tree planting and landscaping between the DuPage River and IL 126.