This week the contractor continued forming and installing shear studs and reinforcement for the rest of the bridge deck, backfilled[...]
Tag: <span>East Extension</span>
Project Update 11/13/25
This week, the contractor continued work on Stage 1 of Naperville Road and progressed on the bridge construction. Activities included[...]
Concrete Pour Scheduled for 11/14/25
A major milestone for the 143rd Street East Extension will be reached this Friday, November 14th with the first of[...]
Project Update 11/6/25
This week the contractor continued to place Stage 1 pavement on Naperville Road and continued excavating for the west compensatory[...]