This week, the contractor continued installing bridge median reinforcement and parapet railing, prepping for mainline pavement, placing asphalt on IL[...]
Tag: <span>East Extension</span>
Concrete Paving and Saw Cutting to begin Thursday, May 21st
Concrete paving of 143rd Street between Naperville Road and IL 126 is anticipated to begin (weather dependent) on Thursday, May[...]
Project Update 5/14/26
This week the contractor continued installing the bridge bicycle railing, laid out locations for trees, brought in equipment for concrete[...]
Project Update 5/7/26
This week the contractor continued installing the bridge bike railing, poured the concrete bridge walls, finished the gateway monument signs,[...]
Project Update 4/30/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/23/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/17/26
This week the contractor poured pavement and curb on Naperville Road, installed storm sewer along southbound IL 59, removed temporary[...]
Project Update 4/9/26
This week the contractor completed the remaining storm sewer work at IL 126 and Naperville Road, installed rebar and poured[...]
Project Update 4/2/26
This week, the contractor constructed the concrete slab on the west side of the bridge approach, prepared the forms and[...]
Project Update 3/26/26
This week the contractor continued installing parapet rebar on the bridge, removing temporary causeways, grading and placing topsoil under the[...]
