February 12, 2026

Project Update 2/12/26

This week, the contractor continued removing bridge deck forms, installing parapet rebar, building and placing aquatic fish cribs in Fletcher[...]

READ MORE
February 5, 2026

Project Update 2/5/26

This week, the contractor continued installing the Fletcher Lake fence posts, constructed fish cribs for the lake, removed bridge deck[...]

READ MORE
January 22, 2026

Project Update 1/22/26

This week, the contractor continued work on the Fletcher Lake retaining wall fence posts and foundations. All other planned activities[...]

READ MORE
January 15, 2026

Project Update 1/15/26

This week, the contractor continued removing bridge deck forms, formed and poured the bridge abutment blockout area, installed Fletcher Lake[...]

READ MORE
December 18, 2025

Project Update 12/18/25

This week the contractor continued work on the retaining wall along Fletcher Lake. Next week, there will be no work.

READ MORE
December 11, 2025

Project Update 12/11/25

This week the contractor continue removing bridge deck forms and installing coping for the retaining wall along Fletcher Lake. Next[...]

READ MORE
December 4, 2025

Project Update 12/4/25

This week the contractor installed conduit for traffic signals at Naperville Road and 143rd St and installed coping for the[...]

READ MORE
November 20, 2025

Project Update 11/20/25

This week the contractor continued forming and installing shear studs and reinforcement for the rest of the bridge deck, backfilled[...]

READ MORE

Showing 1-10 of 150 results