This week the contractor continued placing concrete between Naperville Road and IL 126 and installing trees, bridge parapet railing, bridge[...]
All Updates
May 21st Public Information Meeting
Thank you for attending the May 21st public meeting. We appreciate your time and participation. Here are the exhibits and[...]
Project Update 5/21/26
This week, the contractor continued installing bridge median reinforcement and parapet railing, prepping for mainline pavement, placing asphalt on IL[...]
Concrete Paving and Saw Cutting to begin Thursday, May 21st
Concrete paving of 143rd Street between Naperville Road and IL 126 is anticipated to begin (weather dependent) on Thursday, May[...]
Project Update 5/14/26
This week the contractor continued installing the bridge bicycle railing, laid out locations for trees, brought in equipment for concrete[...]
Project Update 5/7/26
This week the contractor continued installing the bridge bike railing, poured the concrete bridge walls, finished the gateway monument signs,[...]
Open House Public Meeting 5/21/26
Open House Public Meeting Help shape improvements at the intersection of 143rd Street and Wallin Drive at US Route 30.[...]
Project Update 4/30/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/23/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/17/26
This week the contractor poured pavement and curb on Naperville Road, installed storm sewer along southbound IL 59, removed temporary[...]