This week, the contractor continued installing bridge median reinforcement and parapet railing, prepping for mainline pavement, placing asphalt on IL[...]
Blog - Archive
Concrete Paving and Saw Cutting to begin Thursday, May 21st
Concrete paving of 143rd Street between Naperville Road and IL 126 is anticipated to begin (weather dependent) on Thursday, May[...]
Project Update 5/14/26
This week the contractor continued installing the bridge bicycle railing, laid out locations for trees, brought in equipment for concrete[...]
Project Update 5/7/26
This week the contractor continued installing the bridge bike railing, poured the concrete bridge walls, finished the gateway monument signs,[...]
Open House Public Meeting 5/21/26
Open House Public Meeting Help shape improvements at the intersection of 143rd Street and Wallin Drive at US Route 30.[...]
Project Update 4/30/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/23/26
This week the contractor installed storm sewer west of the bridge, continued installing bridge bicycle railing and parapet wall at[...]
Project Update 4/17/26
This week the contractor poured pavement and curb on Naperville Road, installed storm sewer along southbound IL 59, removed temporary[...]
Project Update 4/9/26
This week the contractor completed the remaining storm sewer work at IL 126 and Naperville Road, installed rebar and poured[...]
Project Update 4/2/26
This week, the contractor constructed the concrete slab on the west side of the bridge approach, prepared the forms and[...]