Overall Project Construction Progress

East Extension

Percent Complete 50%
  • Winter 2024
    • Tree removal complete
  • Spring 2024
    • Letting and award to D Construction
  • Summer 2024
    • Began bridge over DuPage River construction
    • Completed IL 126 box culvert extension
    • Began 143rd St box culvert extension
    • Began compensatory storage excavation
  • Winter 2025
    • Bridge over DuPage River substructure construction
    • 143rd St Box Culvert Extension
    • Fletcher Lake Excavation and Filling
  • Spring/Summer 2025
    • Bridge over DuPage River construction
    • Roadway construction
    • IL 126, Naperville Road, and IL 59 intersection improvements
    • Fletcher Lake retaining wall construction
  • Fall 2025
    • Traffic Signals
    • Lighting
    • Roadway construction
  • Spring/Summer 2026
    • Roadway construction
    • Roadway opening
    • Project completion

 Check back for future scheduling updates! 

*Schedule is subject to change.

Overall Project Study Progress

143rd St/Wallin Dr at US Rt 30

Percent Complete 20%
  • Early/Spring 2025
    • Develop and evaluate potential intersection design improvements (alternatives)
  • Summer 2025
    • Prepare a draft concept for intersection improvements
  • Winter 2026
    • Host a public meeting to share proposed intersection improvements and gather community feedback
  • Spring 2026
    • Refine the proposed design based on feedback and further analysis
  • Summer 2026
    • Complete environmental and drainage studies
  • Fall 2026
    • Submit final engineering report to IDOT for review and approval

 Check back for future scheduling updates! 

*Schedule is subject to change.