During the week of 9/23, D Construction mobilized equipment and materials to the site, stripped topsoil for a haul road, and began tree stump removal.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.