Curb installation has been completed throughout the project site. The contractor fine graded the stone within the project limits and continued with earthwork within the easements. Asphalt binder will be placed within the project limits throughout the rest of the week. Johnson Road is open to local traffic only; however, it is recommended that the intersection of Ridge Road and Johnson Road be avoided until traffic signals are installed and functioning in mid-December. Temporary daytime lane closures for paving operations may occur over the next couple months.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.