This week, the contractor worked on building the retaining wall base, placing the aggregate sub-base on IL 126 and 143rd Street heading west, installing storm sewer along 143rd Street between IL 126 and Naperville Road, and assembling parts of the bridge’s steel structure.
Next week, the contractor will continue building the retaining wall, start paving the road at the IL 126 and 143rd Street intersection, installing storm sewer, and working on the bridge’s steel structure.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.