This week, the contractor continued IL 126 excavation and subbase installation, earthwork, and bridge beam installation, and began water main and sewer installation at IL 59 and 143rd Street.

Next week, the contractor will continue with IL 126 excavation and subbase installation, earthwork, bridge beam installation, and water main and sewer installation at IL 59 and 143rd Street.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.