This week the contractor continued temporary pavement construction for Naperville Road and IL 126, storm sewer installation, bridge foundation work, demolition of Cube Smart, and compensatory storage areas excavation. The contractor also began topsoil removal along 143rd St at IL 59, removed the temporary soil retention system from west bank of DuPage River, and moved traffic to Stage 1 configuration on Naperville Road and IL 126.
Next week the contractor will continue storm sewer installation, compensatory storage excavation, roadway embankment, Stage 1 pavement removals on Naperville Road and IL 126, and demolition of Cube Smart.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.