Project Update 5/30/25

May 30, 2025

This week the contractor began beam erection for the bridge over the DuPage River, installation of temporary lighting at IL 59 and 143rd Street, and earth excavation.

Next week the contractor will continue beam erection for the bridge, watermain and storm sewer installation at IL 59 and 143rd Street, and earth excavation.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.