Austin Tyler has completed the installation of the 10’x6’ Box Culvert, and JR Underground completed the borings and installation of 12” and 16” PVC Watermain under the creek at multiple locations. Next week, weather pending, Austin Tyler will continue to work on the watermain, begin road widening operations and culvert replacement for Ridge Road.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.