AT&T is continuing relocation of lines on Ridge Road. The 10’ x 6’ Box Culvert has been completed, and Austin Tyler is close to completing the installation of the 6’ x 5’ Box Culvert.
Work scheduled for next week (weather pending): Austin Tyler will continue the installation of the 6’ x 5’ Box Culvert after redirecting the creek. Austin Tyler will also resume the installation of 16” PVC Watermain from Ridge Road, heading east.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.