This week, the contractor continued rock fill placement in Fletcher Lake, retaining wall installation, and bridge foundation work. The contractor also implemented pre-stage traffic control on IL 59 and begin median removal on IL 59.
Next week, the contractor plans to continue embankment and rock fill work in Fletcher Lake, retaining wall installation, bridge foundation work, and median removal on IL 59.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.