This week, the contractor continued work on the Fletcher Lake retaining wall, bridge foundation, storm sewer installation, and pre-stage pavement on IL 126 and Naperville Road.
Next week, the contractor will continue working on the Fletcher Lake retaining wall, bridge foundation, storm sewer installation, and pavement removal on IL 59. Additionally, demolition will start at Cube Smart, temporary lighting will be installed at IL 59, and temporary pavement will be placed at IL 126 and Naperville Road.
To complete the temporary pavements at IL 126 and Naperville Road, flagger operations will be required. Motorists should anticipate daytime delays due to the paving activities.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.