Last week, Austin Tyler completed the installation of the 6’x5’ Box Culvert, re-routed 300’ of the creek, and resumed installation of 16” PVC Watermain along 143rd Street between Ridge Road and the Creek. This week, weather pending, Austin Tyler will complete installation of the 10’x6’ Box Culvert and continue the installation of 16” PVC Watermain. JT Underground will start the installation of the steel water main casing under the creek to accommodate continued water main installation to the east. AT&T is nearing completion of the underground cable installation as part of their relocation work along Ridge Road and Johnson Road.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.