The sanitary casing was bored under the creek at 2 locations, and 18” PVC sanitary was inserted per plans and specifications. 500’ north of Johnson Rd is complete. Approximately 80% of the sanitary sewer has been installed, and the contractor will continue to work from east to west. All tree removals have been completed throughout the site. Austin Tyler continued to install watermain heading south along Ridge Road, and Rock Enterprises completed erosion control for the site.
Next week sanitary sewer installation will continue west, the install of the 10’x8’ Box Culvert will begin upon delivery of materials, and AT&T will continue relocation of lines, weather pending.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.