  • Project Update 3/12/2026

Project Update 3/12/2026

March 12, 2026

This week the contractor continued installation of bridge parapet reinforcement, the fence along Fletcher Lake, and traffic signal and lighting foundations at the IL 126 and 143rd Street intersection.

Next week the contractor is anticipated to continue bridge parapet reinforcement installation, fence installation along Fletcher Lake, and roadway work at Naperville Road and 143rd Street.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.