This week the contractor continued work on the Fletcher Lake fence, bridge parapet reinforcement installation, and excavation and aggregate subbase installation on Naperville Road.
Next week the contractor will continue the Fletcher Lake fence installation and bridge parapet reinforcement installation.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.