  • Project Update 2/12/26

Project Update 2/12/26

February 12, 2026

This week, the contractor continued removing bridge deck forms, installing parapet rebar, building and placing aquatic fish cribs in Fletcher Lake, installing fence posts along the Fletcher Lake retaining wall, and installing storm sewer along 143rd Street west of IL 59 and along the west side of IL 59 north of 143rd Street.

Next week, the contractor will continue bridge deck form removal, parapet rebar installation, fence post installation, and storm sewer installation along IL 59.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.