This week, the contractor completed the thermoplastic pavement markings along 143rd Street, Ridge Road, and Johnson Road, and the electrician continued installing wire and preparing the 143rd Street and Ridge Road traffic signals to be turned on next week. The contractor also started addressing general clean up and punch list items.
Next week, the new permanent signage will be installed and the west extension of 143rd Street will be open to the public with a working signalized intersection at the Ridge Road intersection.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.