This week, the contractor continued drilling and pouring concrete for the DuPage River bridge foundation and continued work on the east retaining wall, IL 126 and 143rd Street box culverts, and Fletcher Lake excavation.
Next week, the contractor will continue work on the bridge foundation, IL 126 and 143rd Street box culverts, and Fletcher Lake excavation.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.