This week the contractor continued forming the bridge deck, installed shear studs, poured pavement on Naperville Road, continued installation of final section of retaining wall along Fletcher Lake.
Next week the contractor will continue forming the bridge deck and installing shear studs, begin installation of the bridge deck rebar, and continue pavement and curb construction on Naperville Road.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.




