During the week of 9/30, the team focused on stripping topsoil, delivering the silt curtain, mobilizing equipment, and installing the Earth Cam.
During the week of 10/7, the planned activities include installing the silt curtain in Fletcher Lake and the private pond, continuing topsoil stripping, and beginning the temporary access roadway installation.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.