This week, the electrical contractor worked on traffic signal foundations at the intersection of 143rd Street and Ridge Road.
Next week, work on the traffic signals will continue as well as foundations for street lighting along the west extension of 143rd Street. The contractor will also work on permanent landscape restoration.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.