• Home
  • Corridor Overview
    • 143rd Street & Wallin Drive at US Route 30 Intersection Improvements
    • East Extension
    • West Extension
  • Map
  • Schedule
  • Gallery
  • FAQs
  • Documents
  • Contact
  • Home
  • Blog
  • All Updates, East Extension
  • Project Update 1/22/26

Project Update 1/22/26

January 22, 2026

This week, the contractor continued work on the Fletcher Lake retaining wall fence posts and foundations. All other planned activities were suspended due to inclement weather.

 Next week, weather permitting, the Contractor may continue stripping bridge deck forms, install fish cribs at Fletcher Lake, and begin electrical conduit work.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.

  • East Extension
  • Home
  • Village of Plainfield
  • Documents

All rights Reserved