The 143rd St East Extension involves constructing a new road between IL 59 and IL 126 with improvements at both intersections, a bridge over the DuPage River, a new signalized intersection at Plainfield-Naperville Road, and multiple culverts and retaining walls.
Project Highlights
- The new 143rd Street roadway will consist of Portland cement concrete pavement with curb and gutter.
- 143rd Street will consist of two lanes in each direction with a raised median between IL Route 59 and IL Route 126.
- A 960’ 7-Span bridge over the DuPage River and associated river floodway.
- Traffic signal improvements at the intersection of 143rd Street at IL Route 59 to accommodate the East extension.
- New traffic signalized intersections with dedicated turn lanes at 143rd Street and Naperville Road and 143rd Street and IL Route 126.
- Traffic signal interconnection along 143rd Street between IL Route 59 and IL Route 126.
- Reconstruction and widening improvements to Naperville Road and IL Route 126 to accommodate the intersection improvements at 143rd Street.
- LED street lighting along the improved sections on 143rd Street, IL Route 59, Naperville Road, and IL Route 126.
- Shared use path from the DuPage River Trail to IL Route 126 along with bicycle and pedestrian crosswalks at intersections.
- 2,500’ retaining wall along the north side of 143rd Street between Naperville Road and IL Route 126.
- IL Route 126 underpass extension to accommodate roadway widening.
- West Norman Drain box culvert extension on 143rd Street/US Route 30.
- A new closed storm sewer system.
- New water main along the north side of 143rd Street west of the DuPage River.
- Pavement marking and landscaping improvements throughout.
Funding
The total project cost for the East Extension is $82,500,000.
Project Funding
- Village Funding
- Grant Funding
- Village Funding
- Grant Funding
Grant Funding
- Surface Transportation Program (Shared STP)
- Surface Transportation Program (STP)
- Infrastructure for Rebuilding America (INFRA)
- Illinois Competitive Freight Program (ICF)
- State Funding
- Surface Transportation Program (Shared STP)
- Surface Transportation Program (STP)
- Infrastructure for Rebuilding America (INFRA)
- Illinois Competitive Freight Program (ICF)
- State Funding
Funding Allocation
Organization | Amount |
---|---|
Illinois Competitive Freight Program (ICF) | $20,328,000.00 |
Infrastructure for Rebuilding America (INFRA) | $5,000,000.00 |
State Funding | $3,054,347.00 |
Surface Transportation Program (Shared STP) | $17,616,385.00 |
Surface Transportation Program (STP) | $4,500,000.00 |
Village Funding | $31,951,868.00 |
Click HERE for overall Corridor Overview.