Overall Project Construction Progress

West Extension

Percent Complete 65%
  • Winter 2023/2024
    • Tree clearing, installation of sanitary sewer along 143rd St., and water main along Ridge Rd.
  • Spring 2024
    • Install the drainage culverts for 143rd St., Ridge Rd., and Johnson Rd.
    • Earthwork for the new 143rd St. roadway and detention ponds.
  • Summer 2024
    • Continued earthwork for the 143rd St. roadway improvements.
    • Roadway widening improvements along Ridge Rd. and Johnson Rd.
    • Complete water main along 143rd St.
    • Installation of storm sewer along 143rd St.
    • Construction of the new 143rd St. curb and gutter and asphalt pavement improvements.
  • Fall 2024
    • Complete construction of all roadway improvements including final lift of asphalt, shoulder stone, and ditch grading
    • Complete pavement markings, signage, and landscape restoration.
    • Installation of the new permanent traffic signal at 143rd St. and Ridge Rd.
    • Open the new 143rd St. west extension!
  • Winter 2024/2025
    • Complete street light installation

 Check back for future scheduling updates! 

*Schedule is subject to change.

Overall Project Construction Progress

East Extension

Percent Complete 1%
  • Winter 2024
    • Tree removal complete.
  • Spring 2024
    • Letting and award to D Construction.
  • Summer 2024
    • Primary construction begins.
  • Fall 2025
    • Open to traffic.
  • Spring 2026
    • Project completion.

 Check back for future scheduling updates! 

*Schedule is subject to change.