Project Update 8/6/26

August 6, 2026

This week the contractor continued bridge painting, topsoil placement, installation of sight screen fence, lighting and traffic signal foundations, handholds, and conduits, and general site clean-up.

Next week the contractor will continue bridge painting, installation of sight screen fence, lighting and traffic signal items, and general site clean-up.

To view near real time views of construction progress, please check out the Webcam Feed, as well as the latest drone video update, on the Gallery Page.

Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.