This week the contractor continued placing concrete between Naperville Road and IL 126 and installing trees, bridge parapet railing, bridge median reinforcement, traffic signal and lighting conduits, and pavement markings on Naperville Road and IL 126.
Next week the contractor will complete concrete placement, begin curb and gutter installation, continue installing landscaping and bridge parapet railing, and pour the bridge median.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.