This week, the contractor finished installing the light poles and underground electric for the 143rd Street lighting improvements. ComEd is scheduled to provide power to the street lighting within the next two weeks.
Next week, the contractor is expected to resume working on punch list and landscaping items.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.