This week, the contractor continued work on the Fletcher Lake retaining wall and embankment, bridge foundation, compensatory storage excavation, pre-stage pavement on IL 126 and Naperville Road. The contractor also began storm sewer installation and completed curb and medians on IL 59.
Next week, the contractor plans to continue work on the Fletcher Lake retaining wall and embankment, bridge foundation, storm sewer installation, and pre-stage pavement on IL 126 and Naperville Road and begin Stage 1 pavement removal on IL 59.