This week, the contractor resumed work, focusing on installing gabion baskets along the east bank of the DuPage River, completing the temporary causeway, and excavating and backfilling at the West Norman Drain culvert.
Next week, work will continue on constructing the gabion basket wall along the east bank of the DuPage River, excavating and backfilling at the West Norman Drain culvert, and performing compensatory storage excavation.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street East Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.