Austin Tyler has nearly completed the installation of the 10’x6’ Box Culvert with the placement of the cast in place end sections. JR Underground continued the installation of 16” PVC Watermain, with borings under the creek at two locations. AT&T has completed splicing lines on Ridge Road. Next week, weather pending, Austin Tyler will continue to work on the 16” Watermain and complete the Box Culvert hand pours. Road Widening operations for Johnson Road are also anticipated to begin.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.