March 28, 2024

AT&T will continue relocation of lines on Ridge Road. The 18” PVC sanitary has been completed, and Austin Tyler will start the installation of the 10’x8’ box culvert.  Austin Tyler will restart the installation of watermain from Ridge Road and head east next week.

To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.

Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.

Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.