Progress continues on the West Extension project. AT&T is relocating lines on Ridge Road. Less than 500’ of the 18” PVC sanitary remains to be installed for the entire job. Upon the completion of the sanitary (weather pending), Austin Tyler will restart the installation of watermain from Ridge Road and head east next week. Also, next week installation of the 10’x8’ box culvert is anticipated to begin.
To view near real time views of construction progress, please check out the Webcam Feed on the Gallery Page.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.