Last week, Austin Tyler continued the installation of the 20” watermain along Ridge Road and is making progress on the 18” sanitary sewer within the new west extension corridor. Additional tree clearing was performed to accommodate the sanitary sewer, which is now 60% complete.
During the week of March 11th, sanitary sewer installation will continue west along 143rd St., installation of a 6’x5’ box culvert at the creek will begin, and AT&T will start working on underground cable relocation along Ridge Rd. and Johnson Rd.
Thank you for your interest in the 143rd Street West Extension Improvements. Stay tuned to the website for future updates.
Please drive carefully through the construction zone, refrain from cell phone use, and watch for equipment and workers.